Project Schedule
The milestones for the project are anticipated to be as follows:
| completion of CEC permitting process |
July 2010 |
| start of construction |
March 2011 |
| completion of construction |
April 2015 |
| commissioning and initial startup |
January 2015 through October 2015 |
| full-scale operation of the project |
December 2015 |